Commissioning: from first trial to commercial production

Installation ends when the last machine is fixed. Commissioning ends when the plant makes saleable product at its rated output, every shift.

Food technologists testing samples in a quality lab with a glass wall overlooking the production lineIllustrative render · PPCS

The weeks between installation and commercial production decide how quickly a new plant starts paying for itself. Rushed commissioning shows up later as quality complaints, unplanned stoppages and output that never reaches its rated figure.

Six gates

Commissioning works best as a series of gates. The plant moves to the next step only when the checks of the previous one are closed and written down.

1 MECH. COMPLETIONinstalled as drawnsafety checks2 DRY RUNmotors, directionsinterlocks, no product3 WATER TRIALleaks, flowstemperatures, CIP4 TRIAL BATCHESreal productsettings recorded5 PERFORMANCErated outputquality held6 HANDOVERSOPs, trainingdocumentsEACH STEP IS A GATEThe plant moves on only when the checks of the step before it are closed and recorded.
Fig. 1 — Six gates between installed and in production

Mechanical completion

Everything installed as drawn, with guards, earthing and safety devices in place.

Dry run

Motors, directions of rotation, interlocks and controls tested without product.

Water trial

Leaks, flows, temperatures and cleaning systems tested with water before food is involved.

Trial batches

Real product, small quantities, with every setting recorded so that what works can be repeated.

Performance

The line run at its rated output for long enough to show that output and quality hold together.

Handover

Standard operating procedures, training and documents handed to the team that will run the plant.

A recipe that works once is a trial. A recipe that works every shift, with every operator, is a product.

Product standardization

Alongside the machines, the product itself has to be fixed: ingredients, quantities, process times and temperatures, and the checks that confirm each batch. This is what lets a plant deliver the same product on its hundredth day as on its first.

Who should be in the room

  • Machinery suppliers, for their equipment.
  • The client's operating team, who will run the plant afterwards.
  • An engineer coordinating the sequence and recording the results.